Comment on credit EW-2
EW -2
Pg 1; goal
The goal should be consistent with storm water runoff requirements for federal development projects: “. . . maintain or restore, to the maximum extent technically feasible, the predevelopment hydrology of the property with regard to the temperature, rate, volume, and duration of flow.”
Energy Independence and Security Act of 2007
NPS-SC
EW -2
Pg 5 to 12
This section is somewhat confusing, redundant, and long. Consider reorganizing and editing to remove unnecessary text/graphics and focus the discussion on how roads cause runoff flow problems, how elevated runoff flow can adversely affect the downstream environment, and how sustainable site planning, design, construction, and maintenance strategies (LID BMPs) can mitigate these adverse effects.
NPS-SC
EW -2
Pg 3; Item 2
Change “This is practice is” to This practice is”
NPS-SC
EW -2
Pg 2; 3rd bullet
Change “Protection” to “Protect”
NPS-SC
EW -2
ROWs are typically not delineated for roads in parks. Consider replacing ROW with “road corridor” or “roadway”
NPS-SC
EW-2
Pg 1; goal
The goal should be consistent with storm water runoff requirements for federal development projects: “. . . maintain or restore, to the maximum extent technically feasible, the predevelopment hydrology of the property with regard to the temperature, rate, volume, and duration of flow.”
Energy Independence and Security Act of 2007
NPS-SC
Greenroads Manual Version 1.0 Review
You must be logged in to the Greenroads website in order to post comments on the manual. If you already have an account, please log in using the green login box in the upper right portion of the screen. If you do not have an account but wish to comment, please sign up for one here.
Thanks,